Burndown Chart Calculator

Track sprint progress: ideal burndown vs actual remaining work with variance analysis.

Formulas:
Ideal Daily Burn = Total Points / Sprint Days
Ideal Remaining at Day N = Total − (Ideal Daily × N)
Variance = Actual Remaining − Ideal Remaining
Required Velocity = Remaining / Days Left

Reading a Burndown Chart

  • On track: Actual line follows ideal line closely
  • Behind: Actual line is above ideal (more work remaining than expected)
  • Ahead: Actual line is below ideal (team is completing work faster)
  • Flat line: No progress — blockers or scope creep

When to Worry

If at mid-sprint you've completed less than 40% of work, the sprint is at risk. Consider reducing scope, adding resources, or carrying items to the next sprint.